Project: New Doha International Airport Project (NDIA)
Main Contractor: CCC / TCC JV
End User: NDIA & Qatar Airways
Scope of Work: Design & Engineering, Procurement, Fabrication, Painting and Erection of Structural Steel and Miscellaneous Steel works for the following Buildings / Packages (CP-93, CP-95 & CP-96):
- Main Fire Station Building
- Satellite Fire Station Building
- General Aviation Terminal Building
- General Aviation Hangar Building
- Solid Waste Handling Facility Building
- Administration Blocks (A&B) Building
Status: Completed
Quantities:
- Main Fire Station: 290 tons
- Satellite Fire Station: 290 tons
- General Aviation Terminal: 320 tons
- General Aviation Hangar: 540 tons
- Solid Waste Handling Facility: 480 tons
- Administration Blocks (A&B): 120 tons